After installation of the wall plastering swing stage platform, inspections should be took.

1.     Check the installation of the roof mechanism system, which should be fixed firmly, the cantilever length and connection mode are correct.

2.        The steel wire rope should be no kink, no loose, no worn and no broken.

3.        The safety locks and limit switches of the swing stage platform are effective and reliable.

4.        The motor hoist has no abnormal sound, no overheating, and can start  and brake normally.

 