Concentrate on quality of the construction hoist and suspended platform, never forget original intention!

KNOWLEDGE

Home  > ABOUT US  > KNOWLEDGE  > 

The load capacity and working voltage of electric powered hanging platforms

The load capacity and working voltage of electric powered hanging platforms

2021-07-08

Before daily operation, check all parts of electric powered hanging platform is normal.

Take no-load test after inspection, when the no-load test is normal, we can use the aerial construction platform.

The loading material in the working cradle should be evenly distributed, and can not be overloaded.

 Normally, the limit load capacity of aerial lifting platform should not be great than 80% of the rated load capacity.

 If  the working cradle is fully loaded or lifting  frequently, the lifting gondola platform will be damaged, thus affecting the normal construction operation.

The voltage of the electric hanging platform is mainly for the control box and electric switches . Because they need to be energized in the process of use, there will be a voltage.

The normal requirements are: the rated voltage of the electrical control box and the electric switches shall not exceed 220V, and the total power shall not exceed 3KW, and shall be grounded to ensure the safety of electricity use.